Safety Interlocks
Safety interlocks are the automatic barriers between a developing process deviation and a catastrophic outcome. This page covers what interlocks fire heaters use, why they exist, how they relate to the BMS, and what an operator must know to work safely around them.
Interlock categories
Fired heater interlocks fall into four functional groups. Every trip signal belongs to one of these — understanding the group tells you immediately what hazard the interlock is protecting against.
Cause & Effect — typical interlock matrix
The Cause & Effect (C&E) matrix is the definitive reference for what each trip does and why. The table below represents typical refinery practice. Your site-specific C&E matrix — issued under document control — takes precedence over all generic guidance.
| Cause / Tag | Condition | Type | Effect | Hazard prevented |
|---|---|---|---|---|
| Feed flow — low low FSLL-xxx |
Flow falls below minimum safe throughput | TRIP | Close fuel SDV, fire BMS trip | Dry firing / tube overheating / coking |
| Coil outlet temp — high high TAHH-xxx |
COT exceeds maximum design temperature | TRIP | Close fuel SDV, fire BMS trip | Tube metallurgical failure, cracking overrun |
| Coil outlet temp — high TAH-xxx |
COT approaching trip setpoint | ALARM | Operator alert — reduce firing | Early warning before TAHH |
| Tube skin temp — high high TSHH-xxx |
Skin temp exceeds tube design limit | TRIP | Close fuel SDV, fire BMS trip | Tube creep damage / rupture |
| Flame detection — loss BE-xxx (UV/IR) |
No flame confirmed within scan period | TRIP | Close all fuel SDVs immediately | Unburned fuel accumulation / explosion |
| Fuel gas pressure — low low PSLL-xxx |
FG header pressure too low to sustain flame | TRIP | Close fuel SDV, fire BMS trip | Flame instability and blowout |
| Fuel gas pressure — high high PSHH-xxx |
FG pressure exceeds burner design rating | TRIP | Close fuel SDV, fire BMS trip | Flame liftoff, combustion instability |
| Draft fan — failure ZSL-xxx (current) |
Fan current loss / vibration high | TRIP | Close fuel SDV, fire BMS trip | Air-short combustion, CO, firebox pressurisation |
| Firebox pressure — high high PSHH-firebox |
Positive firebox pressure (loss of draft) | TRIP | Close fuel SDV, fire BMS trip | Hot gas ejection, explosion risk at openings |
| Feed flow — low (first alarm) FAL-xxx |
Flow falling, approaching FSLL | ALARM | Operator alert — investigate | Pre-trip warning, allow corrective action |
Layers of protection — where interlocks sit
Interlocks are one layer in a defence-in-depth stack. Understanding the full stack shows why any single layer failure is not immediately catastrophic — but also why bypassing a layer removes protection that assumes the layers below it will hold.
What to do when an interlock fires
An interlock trip is a message: a condition outside the safe envelope has been detected. The correct sequence is always the same, regardless of which interlock fired.
Spurious trips — when the interlock fires incorrectly
A spurious trip is an interlock action not caused by a real process hazard — typically instrument failure, sensor fouling, or logic solver faults. They are operationally disruptive, but the correct response is still to treat the trip as valid until the cause is confirmed to be instrumentation.
Common causes of spurious trips and their investigation approach:
| Common Cause | What to Check | Corrective Action |
|---|---|---|
| Flame detector lens fouling | Cross-check against other flame detectors on same burner; inspect lens physically | Clean lens; functional test before restart; schedule replacement if recurrent |
| Flow transmitter impulse line blockage | Compare to independent flow measurement; check DP transmitter zero | Clear impulse lines; verify transmitter reads correctly against known flow |
| Thermocouple failure (COT) | Cross-check against redundant thermocouple; check continuity and reading drift history | Replace thermocouple; do not reset TAHH bypass without replacement |
| Pressure transmitter calibration drift | Compare to local gauge; check calibration date | Recalibrate or replace; enter MOC for temporary bypass if continued operation required |
| Power supply / signal wiring fault | Check SIS panel diagnostics; continuity check on field wiring | Restore supply or repair wiring; notify instrument technician before restart |
Interlock bypass management
Occasionally, operational necessity or instrument maintenance requires that an interlock be temporarily bypassed. This is a managed activity — not a field decision. The following requirements apply in every well-run facility, regardless of the specific bypass procedure document.
- During proof testing of the interlock (testing that the interlock works — it must be bypassed to test the final element without tripping the unit).
- When a sensor has failed and a replacement is not yet available, requiring temporary compensating measures.
- During startup conditions where a permissive cannot yet be met but the associated hazard is managed by other means.
- Increased operator surveillance frequency — typically 15–30 minute manual checks of the bypassed parameter.
- Temporary high-alarm at a lower setpoint to give earlier operator warning.
- Reduced throughput or firing rate to reduce the rate of approach to the hazardous condition.
- Continuous presence of a qualified operator at the panel during the bypass period.
- Active bypasses must be explicitly communicated to the incoming operator.
- The incoming operator must acknowledge the bypass and the compensating measures in place.
- An open bypass that is not re-confirmed and re-approved at shift change must be removed.
Proof testing — confirming the interlock will work
An interlock that is never tested may have failed silently. SIS and BMS proof testing verifies that each sensor, logic solver, and final element (SDV) will function correctly on demand. Testing intervals are set by the SIL assessment — typically annual for SIL 2 systems. The operator's role in proof testing:
- Coordinate with instrument and operations to schedule tests during planned shutdowns or low-criticality windows where possible.
- Confirm unit conditions before testing — some tests require partial load reduction or process isolation.
- Witness SDV stroke tests and confirm valve travel meets specification.
- Do not accept a "pass" on a partially-stroked valve test if full closure is required for the interlock function.
- Sign the proof test record — this forms part of the SIL verification audit trail.